Current City Projects

North Mechanic Street Reconstruction
The City of Lebanon will be completing a full reconstruction of North Mechanic Street from East Warren Street to its end, north of New Street. The construction activity will include a new roadway surface, installation of a new storm sewer system, new public sidewalks and a replacement of utilities as needed. This project is anticipated to begin mid to late August with an estimated completion date of: Utilities in winter 2022; Final paving in spring 2023.

2023 Urban Paving Program
The City of Lebanon in conjunction with the Ohio Department of Transportation is working to resurface sections of SR63, SR48, and US 42 and replace deteriorated curb & gutter, sidewalks, driveway aprons, and install ADA compliant handicap ramps. This include includes West Main Street (SR 63) from the City’s west corporation limit to the intersection with South Broadway (US 42), continuing north on South/North Broadway (US 42/SR48) to the intersection with East Warren Street (US42), and continuing East Warren Street/Columbus Avenue (US42) to the intersection with SR48 Bypass. The total project length is 3.97 miles and constitutes 11.89 lane miles. Construction for concrete began at the end of April and final paving is scheduled for the end of July.

2023 Concrete and Paving Program
The City of Lebanon will be replacing all deteriorated curb & gutter, sidewalks, driveway aprons, catch basins and pavement along the following streets:  La Luz Boulevard, Oak Street, Summit Street, East Silver Street, East Mulberry Street, West Orchard Avenue, Cook Road, Catalpa Ridge, Lance Court, Grant Drive and Taft Drive. Construction to begin in June and be completed by the winter. 

Cherry Street Reconstruction
The City of Lebanon will be completing a full reconstruction of Cherry Street from East Main Street to New Street. The construction activity will include a new roadway surface, installation of a new storm sewer system, new public sidewalks and a replacement of utilities as needed. This project is anticipated to begin in August and will have two phases. Construction from New Street to Warren Street has an estimated completion date in winter 2023; Construction from Warren Street to Main Street estimated to be complete in summer 2024.

Pleasant Street Water Main Extension
The City of Lebanon will be installing a new water main along East Mulberry Street from Mechanic Street to North Broadway Street. The project will connect the water mains on each street by adding 360 feet of  8” water main along Pleasant Street.  As well as installing new water service lines and meters to properties along the project corridor. The replacement project is being coordinated with the resurfacing of East Mulberry Street and is scheduled to start in July 2023.

Reeders Run Sanitary Sewer Extension – Phase 2
The City of Lebanon will be extending sewer along  W. Main Street starting Markey Road and going 2100 feet west.  The project will connect with Phase 1, which was completed in 2022 and extended the sewer from Glosser Road to Markey Road.  The extension is being built for future development along the corridor.  Construction is set to start in July and be completed in early fall. 

Kingsview Dr. Bridge Replacement Project
City of Lebanon in coordination with the Ohio Department of Transportation (ODOT) proposes to replace the Kingsview Drive bridge (SFN 8360235) over Turtle Creek in in the City of Lebanon, Ohio. Small right-of-way impacts to surrounding properties are expected. The vehicular bridge will be closed to traffic for approximately 40 weeks during construction. Traffic control and roadway closure signs will be posted, and the signed detour will be Colombia Road to Mason Morrow Millgrove Road to Turtlecreek Road for an approximate detour length of 3.5 miles. The pedestrian bridge that is part of the Lebanon Countryside Trail will be closed for no more than two weeks, in order to safely replace the Kingsview Drive bridge. Pedestrian access will be maintained on the adjacent bridge during the majority of construction. Construction work is expected to begin in Fall 2024 and will last approximately six months. For more information, click here